April 2022
Design Phase begins
Project design will continue until late October 2022. Most of the public input is anticipated to occur between March and July 2022.
 
 
March 25 → April 08 2022
First public survey open
 
 
April 2022
Geotechnical assessment
 
 
July 22 → August 18 2022
Second public survey open
 
 
September 2022
Permitting
 
 
February 2023
Bid the playground project
Two or three week bid period.
 
 
April 2023
Begin construction
We anticipate end of construction will be mid-August 2023, then fun begins.