April 2022

Design Phase begins

Project design will continue until late October 2022. Most of the public input is anticipated to occur between March and July 2022.

March 25 → April 08 2022

First public survey open

April 2022

Geotechnical assessment

July 22 → August 18 2022

Second public survey open

September 2022

Permitting

February 2023

Bid the playground project

Two or three week bid period.

April 2023

Begin construction

We anticipate end of construction will be mid-August 2023, then fun begins.